IZAJE TORRE DEHETANIZADORA MALVINAS PROYECTO CAMISEA

ALE HEAVYLIFT    was contracted to erect a deethanizer column as part of a plant expansion project in the Peruvian jungle.

In order to successfully complete the erection of the 463te, 51m high column, ALE used a bespoke 60m self-erecting gantry, stabilised with a strand jack system, comprised of two 500te units and a tailing gantry with a hydraulic 500te lifting unit for retaining.

 

DOWNLOAD : NEWSLETTER Nº7

 

 

 

 